PERENCANAAN SISTEM DRAINASE BERWAWASAN LINGKUNGAN JALAN TOL GEMPOL PAKET I
Abstract
The 5,500 m Gempol Toll Road Package I needs an environment-oriented drainage system design completed with infiltration well made at an interval of 100 m of rainwater function and maintain ground water level.
The design needs some data of situational map, long-section, and rainfall from 3 nearby stations: Gempol, Winong, and Bareng, in 2002-2012. The rainfall data were processed to analyze the maximum rainfall rate; Mean Algebra Method was employed for local rainfall calculation, and Log Pearson type III was used for the 10-year design rainfall which results in 121.281 mm.
The calculations result in 0,023 m³/dt rain water discharge flow to the river; rainwater tank dimensions of 2.25 m2 in area and 3 m in depth; 54 tanks on the left and 55 tanks on the right; and two 0.6 m Æ pre-cast culvert rings. The rectangular drainage channels were of stone river with dimensions of 0.7 m in width and 0.6 m in depth. The project takes 204 workdays at IDR Rp 9.633.074.000 cost.
Keywords: drainage system; infiltration well; design flood.
Full Text:
PDFDOI: http://dx.doi.org/10.33795/prokons.v9i1.83
Refbacks
- There are currently no refbacks.
Copyright (c) 2017 PROKONS Jurnal Teknik Sipil
INDEXING :
The following is an indexing list that includes the journal of the Prokons, published by the Civil Engineering Department, Politeknik Negeri Malang
_______________________________________________________________________________________________
Jurusan Teknik Sipil Politeknik Negeri Malang
Jalan Soekarno-Hatta No. 09, PO BOX 04 Malang 65141
Telp 0341-404424 || Fax 0341-404420
ISSN Print (1978-1784) || Online (2714-8815)
Email : prokons@polinema.ac.id
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License .