PENGENDALIAN MUTU PEMBANGUNAN RUMAH SAKIT DI MOJOKERTO PROVINSI JAWA TIMUR

Romy Fansuri Yahya, Sumardi ,, Dandung Novianto

Abstract


The  project was undertaken by CV. Dwi Mulya Jaya with the contract price of IDR. 9,431,000,000.00 on 150 calendar days. An alternative project planning was in need to complete the project on time, cost, and quality

The project planning included; 1) site layout; 2) traffic managemnet; 3) implementation method; 4) scheduling; 5) cost; 6) quality and 7) safety.

Technical drawings, technical specifications, bill of quantity, and work unit price of Mojokerto 2016 were needed. Microsoft Exel 2013 and Microsoft Project 2007 were employed to determine the project price and scheduling.

The planning results in: 1) direction kit in the front of the project, on the right side; 2) one-gate system; 3) two-zone system and cast-in-situ method; 4) on 147 calendar days; 5) at IDR 8,188,864,607.06; 6) the quality meeting the specification and Standard Operational Procedure; 7) applying safety rules on  Mondays.

 

Keywords: project planning, site layout, implementation method.


Full Text:

PDF


DOI: http://dx.doi.org/10.33795/prokons.v12i1.154

Refbacks

  • There are currently no refbacks.


Copyright (c) 2019 PROKONS Jurnal Teknik Sipil



INDEXING : 

The following is an indexing list that includes the journal of the Prokons, published by the Civil Engineering Department, Politeknik Negeri Malang

          

   

     

 

_______________________________________________________________________________________________

Jurusan Teknik Sipil Politeknik Negeri Malang

Jalan Soekarno-Hatta No. 09, PO BOX 04 Malang 65141

Telp  0341-404424 ||  Fax  0341-404420

ISSN  Print (1978-1784) ||  Online (2714-8815)

Email  : prokons@polinema.ac.id

 

Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License .